Since January, 2003

August 6, 2005

May 26, 2013
4th at River St., Looking West (see more)

There's a lot going on over yonder at 11th Street these days, as the initial 11th Street Bridges project continues toward its expected completion next year while the now-funded Phase 2 work is starting to get underway.
I was able to arrange a tour last week (thank you, bridge folks!), and have put together a photo gallery of the most interesting shots.
However, there's a lot going on and so I'm going to break out some of the information here as well. (But go look at the gallery too!)
New Ramps from/to 11th Street Local Bridge
By the end of the month (or maybe even by the end of the week), two new ramps on the 11th Street Local Bridge will open, providing access to southbound I-295 from the local bridge and to the local bridge from northbound DC-295. There are signalized intersections at both ramps, with turns allowed in each direction. And, once construction is finished to make 11th Street two-way from O Street northward, commuters driving north on 295 will be able to use the new ramp to the local bridge to then arrive directly at the Navy Yard's entrance gate at 11th and N.
Southeast Blvd., and Outbound Freeway Traffic
This week saw the first of the lane closures that within a few months will signal the end of the SE Freeway east of 8th Street. Once all lanes are closed, traffic taking the old two-lane flyover to outbound I-695 will be temporarily routed onto the completed-but-not-opened inbound flyover connecting I-695 and I-395. This will allow for the razing of the old outbound flyover, and construction of a new three-lane flyover in the gap between the old and new ones. The filling of the old sunken freeway will also begin, for the new at-grade Southeast Blvd.
Old Outbound Bridge Demolition
The old outbound 11th Street Bridge is now little more than a bunch of old girders, which are starting to be removed. Soon, all that will be left will be the river piers, though two of those will be used to create viewing platforms that will be accessed via walkways from the new 11th Street Local pedestrian path. (And can be reused if anyone ever decides to pony up the millions needed to create the 11th Street Recreation Bridge.) In the meantime, work continues on the downriver edge of the new local bridge, to get it to its full four-lane-plus-ped-path width.
But there's more than just these items and photos. There's photos of the under-construction ramp that in about three months will take traffic from outbound I-695 to northbound DC-295, plus the big piles of dirt waiting to be used to fill in the eastern part of the Southeast Freeway, and the work on the ramp from 11th Street to westbound I-395, and more. So go look at the entire gallery. (I've also incorporated some of the new photos into my 11th Street Bridges project page, to go with the before-and-afters.) I also wrote in more detail about the Phase 2 projects a few months back.
 

See All Current News Items

Comments

KLB says: (9/19/12 9:35 AM)
From the "entire gallery" page, "However, once the sunken freeway lanes are closed, traffic currently running to outbound I-695 on the ramp seen at far left will be diverted onto this new flyover, which allows for the demolition of the old two-lane outbound flyover and construction of a new three-lane one."

Will the inbound and outbound traffic share the new inbound ramp, or will it just be outbound traffic until the new outbound flyover is completed?

JD says: (9/19/12 9:39 AM)
Dangit, why did you ask the one question I specifically hoped no one would ask, since I forgot to ask myself? :-) My initial guess is that it would just be outbound traffic until the new flyover is finished, but I honestly don't know. I'll see what I can find out, or maybe before long they'll release actual construction documents instead of the concept ones.


bkt says: (9/19/12 9:56 AM)
JD, Do you know what the plans are for the northbound exit onto 295/695 from Howard Road? I take 295 North from Bolling to Rt 50 and the traffic merging from the right side has to merge over 2 lanes very quickly to the left exits for 695 which leads to complete congestion chaos at rush hour. This seems like a fail to me, but maybe there's another phase coming with a 'fix'???

JD says: (9/19/12 10:57 AM)
@bkt, I have to admit that I don't pay as close attention to the design and issues on the east side of the river, so I don't know specifically in terms of the current 11th Street Bridge construction.

Long term, the real solution is probably the huge new *real* interstate interchange at 295/South Capitol Street/Suitland Parkway, to be built with the new Douglass Bridge.

Short term, I do think that they're hoping the new exit about to open to the 11th Street Local Bridge will at least take traffic going to the Navy Yard out of the two left lanes, which I assume would include some of that Howard Road ramp traffic.

Also, there's going to be a ramp from the east side of the 11th Street Bridge to northbound DC-295 (ramp C-2 on the link below) so that maybe some of the local Anacostia traffic wouldn't be trying to get on at Howard Road, but instead there?

link




Maelstrom says: (9/19/12 11:13 AM)
@KLB - beat me to the question. Personally, I think they could fit everyone on the new flyover without losing capacity, but I don't think they will only do that if they need to tear out the old inbound flyover for the sake of the fill work below. Consider that once you close the old inbound flyover, you have no exits between M street and D street SW on 695/395N. I am somewhat suprised by the announcement that the outbound traffic will be diverted onto the new flyover. It was one of the options I had anticipated, but it's an ugly one because they will have to tear out the shiny new bridge edge that they built between the inbound and outbound freeway bridges and the pile of rocks in between the bridges to divert the traffic. More than the re-purposing of the fill for the off ramp from SE/SW @11th, this is a case where new work will need to be ripped out and re-done later.

terpsichorean says: (9/21/12 9:29 AM)
Hi, I live on upper NE side of the Hill (practically Rosedale). I work in Crystal City, and until Monday I took 17th St and made a left onto the Barney Circle/RFK entrance to get to work every morning. Each day this week I have tried a different route to attempt to cut across the Hill to get to the 3rd St SE entrance, but there seems to be no efficient way to do this (traffic, lights, etc). Does anyone have a recommendation for us NE Hill folks? Should I just start taking 295 to get to 395, and avoid the Hill until the 11th St bridge opens? This has drastically changed my once beautifully short commute. So frustrating...Help!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2014!

Tell readers about your
apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
Sophia Monster on Lineups Announced for: "Rudy" was slated to give a motivational speech at...
smokie on Grosvenor Looking for: aw! Well fair enough.
JD on Grosvenor Looking for: My methods are proprietary. :-) (JES, fixed your link)
smokie on Grosvenor Looking for: @ JES, annoying they can't get the name right; to be fair, I...
Latest News
  
For past mile markers in the neighborhood's evolution,
see my Near Southeast DC Timeline.

 
Thousands and thousands of photos showing the neighborhood changing. More than 150 buildings no longer with us. All the news, since 2003. Photos from various archives showing the neighborhood in the more distant past. Maps from the early 1900s. Overhead Photo Comparisons: 1949, 1988, 2002-2008. All Blog Entries, 2003 - Present Major Events, 1799 - Present A series of blog entries looking at the neighborhood's history.
Near Southeast's Rearview Mirror
Today in (Recent) Near Southeast History


City Government Data for Near Southeast
Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
100 B/O L ST SE   THEFT F/AUTO /  04/05/14
1500 B/O SOUTH CAPITOL ST   THEFT /  04/04/14
330 B/O K ST SE   THEFT /  04/04/14
16 B/O M ST SE   THEFT /  04/04/14
700 B/O L ST SE   THEFT /  04/03/14

Active Public Space Permits Archive  
1011 1ST ST SE    COLIN CLARK 
Pending
excavation; new  
 03/03/14
to
05/01/14
    COLIN CLARK 
Approved (Pending Payment)
paving; landscaping; new  
 04/23/14
to
06/27/14
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
1201 M ST SE    Michael Manoski 
Pending Document
excavation  
 05/06/13
to
05/05/14
1333 M ST SE    WASHINGTON GAS 
Assigned
excavation  
 05/01/13
to
04/30/14
1111 NEW JERSEY AVE SE    NJA Associates LLC 
Assigned
paving; streetfixture; landscaping; excavation; new  
 06/03/13
to
06/02/14
301 TINGEY ST SE    Chuchart Kampirapang 
Assigned
 
 06/07/13
to
06/06/14
    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
04/09/14 
MILLER?LONG
AH1400386 / CONSTRUCTION
AFTERHOURS TO TAKE DOWN TOWER CRANE WITH 200 TON CRANE SAT ? SUN 4 / 12 / 2014 AND 4 / 13 / 2014 FROM 5AM TO 9PM
   
04/21/14 
TOLL DC LP / DELAWARE ELEVATOR INC
EN1401543 / SHOP DRAWING
TYPE OF ELEVATOR : ONE (1) MRL / STEEL / FRONT OF BLGD / PASSENGER. (VELOCITY RIVER PARK / PLASE 2 / CAR A)
1381 1ST ST SE   
04/07/14 
DISTRICT OF COLUMBIA /
SB1400233 / CONSTRUCTION
INSTALLATION OF 3 GEO SOIL BORINGS TO A DEPTH OF 30FT 4' DIAMETER USING GEOPROBE 3 OUT OF 3 ARE TMMW
1212 4TH ST SE   
04/09/14 
GSA GSA / BRIAN FREW; GSA GSA; JOSEPH RICHARDS
E37554102 / SUPPLEMENTAL
1000 5TH ST SE   
04/04/14 
DC HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
B1404942 / CONSTRUCTION
TEMPORARY CONSTRUCTION TRAILER TEMPORARY CONSTRUCTION FENCE AROUND THE PERIMETER OF THE PROPERTY AND TWO PORTA POTTIES AND TO INCREASE TO A TOTAL OF 4 PORTA POTTIES AT THE PEAK OF CONSTRUCTION. TRAILERS WILL BE ON BLOCKED ON TEMPORARY CMU BLOCKS - POWERED FROM TEMPORARY SERVICE BY PEPCO TRAILERS WILL BE EQUIPPED WITH RESTROOM SYSTEM THAT WILL BE SERVICED - NO PLUMBING LINES AS THEY ARE SELF CONTAINED
   
04/11/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
SH1400015 / CONSTRUCTION
SHEETING ? SHORING FOR NEW COMMUNITY CENTER
1220 12TH ST SE   
04/15/14 
WASHINGTON GAS LIGHT CO / STEPHEN R. HOLMAN
P1404623 / SUPPLEMENTAL
1015 HALF ST SE   
04/09/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
B1405731 / CONSTRUCTION
INTERIOR RENOVATION FOR 1ST FLOOR SERVICE CORRIDOR. PARTITIONS DOORS MECHANICAL ELECTRICAL AND LIFE SAFETY.
75 I ST SE   
04/07/14 
DRI DEVELOPMENT SERVICES LLC / JOSE S ALVARADO; DRI DEVELOPMENT LLC; JOSE S ALVARADO
E16994763 / SUPPLEMENTAL
   
04/07/14 
DRI DEVELOPMENT SERVICES LLC / JOSE S ALVARADO; DRI DEVELOPMENT LLC; JOSE S ALVARADO
E10943636 / SUPPLEMENTAL
409 I ST SE   
04/07/14 
SCOTT A FAULK TRUSTEE / RALPH THREATT
E1404619 / SUPPLEMENTAL
309 K ST SE   
04/06/14 
GERRITT LANG
PC61450444 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 GAS APPLIANCE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
306 L ST SE   
04/17/14 
MICHAEL THOMPSON
B1311538 / CONSTRUCTION
1.CRAWL SPACE FOUNDATION REPAIR CRAWL SPACE UNDERPINNING AND EXCAVATION 2. ADD CONCRETE SLAB AND EGRESS WINDOW. 3. UPGRADE EXISTING ELECTRICAL PLUMBING AND MOVE MECHANICAL CLOSET
601 L ST SE   
04/21/14 
DC HOUSING AUTHORITY / ANGEL REYNOLDS
SH1400035 / CONSTRUCTION
TEMPORARY SHEETING AND SHORING REQUIRED TO ALLOW CONSTRUCTION PF NEW BUILDING AT 601 L ST SE.
50 M ST SE   
04/17/14 
KEN FINKELSTEIN ENGLEWOOD LLC / DAVID BOOKBINDE ECS MID-ATLANTIC LLC
SB1400244 / CONSTRUCTION
A TOTAL OF 6 BORINGS WILL BE ADVANCED ACROSS THE PROPERTY WITH A GEOPROBE DRILL RIG TO A DEPTH OF 25 FEET BELOW SURFACE GRADE. THE DIAMETER OF THE BOREHOLE WILL BE 2.25 INCHES. SOIL WILL BE SCREENED THROUGHOUT THE DEPTH OF EACH BORING AND EACH 5-FOOT COMPOSITE SAMPLE WILL BE ANALYZED. GROUNDWATER WILL BE COLLECTED FROM TEMPORARY WELLS IN THREE BORINGS IF ENCOUNTERED. ALL BORINGS WILL BE GROUTED WITH APPROVED BENTONITE SLURRY UPON COMPLETION. SEE WORKPLAN FOR ADDITIONAL DETAILS.
901 M ST SE   
04/14/14 
CARLTON RAY / DANIEL SCHAALE
AH1400397 / CONSTRUCTION
EXCAVATION IN ROADWAY
1201 M ST SE   
04/14/14 
CARLTON RAY / DANIEL SCHAALE
AH1400396 / CONSTRUCTION
EXCAVATION IN ROADWAY
   
04/14/14 
SAMUEL PAXTON
PC81065987 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 PLUMBING FIXTURE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
86 N ST SE   
04/17/14 
BELFAST VALLEY CONTRACTORS / KIM MITCHELL CDKM CONSULTING LLC
TC1400011 / CONSTRUCTION
ERECT TEMPORARY TOWER CRANE AT 1ST AND N ST SE
1000 NEW JERSEY AVE SE   
04/14/14 
PHILIP BROWN
PC47087282 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 GAS APPLIANCE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
1500 SOUTH CAPITOL ST SE   
04/07/14 
WASHINGTON NATIONALS STADIUM LLC / FRED GRIFFITH; WASHINGTON NATIONALS STADIUM LLC; JAY LIVESAY
E53144683 / SUPPLEMENTAL
301 TINGEY ST SE   
04/11/14 
NA NA NA
EHOP1490466 / HOME OCCUPATION
   
04/11/14 
NA NA NA
EHOP1490467 / HOME OCCUPATION
301 WATER ST SE   
04/04/14 
FC LUMBER SHED LLC / RICHARD V CAREY
P1404549 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Projects Underway
Twelve12/Yards
Park Chelsea
Southeast Blvd.
River Parc
  
Nationals Park
Visiting Nats Park
What's New Around the 'Hood
Food Options Map
Parking/Transportation
Ballpark Construction Photos
Stadium Event Photos
In the Pipeline
Hampton Inn
1111 New Jersey
800 NJ/Whole Foods
Lofts at Capitol Quarter
Ballpark Square
New Douglass Bridge
Yards at DC Water
Virginia Ave. Tunnel
99 M St.
Monument/Half Street
Community Center
Capper Apartments
250 M Street
Florida Rock
909 Half Street
Congressional Square
1000 South Capitol
SC1100
New Marine Barracks
Factory 202/Yards
Nat'l Comm. Church
Completed
Lumber Shed ('13)
Boilermaker Shops ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts/Yards ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 NJ Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
Nationals Park ('08)
70/100 I ('08)
Seniors Bldg Dem. ('07)
400 M ('07)
SoCap Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Overviews
Capper/Carrollsburg
Ballpark District
New Jersey Ave.
M Street
South Capitol St.
WASA
The Yards
Lower 8th Street
East M Street
Boathouse Row


Links of Interest

JDLand.com Wins 2008 Knight-Batten Citizen Media Award
As part of the Knight-Batten Awards for Innovations in Journalism, JDLand was given the 2008 Citizen Media Award. Read all about it.

Capitol Riverfront Business Improvement District
Covering Near Southeast & Buzzard Point.

Studies/Initiatives/Government Documents:
11th Street Bridges EIS
South Capitol St. Bridge EIS
South Capitol Gateway Corridor/Anacostia Access Study
Anacostia Riverwalk Trail
NCPC's New Vision for South Capitol Street (2005 Update)
Anacostia Waterfront Initiative (2005)
Near Southeast Draft Urban Design Framework (2003)
Urban Land Institute South Capitol Street Corridor Report (2003)
Neighborhood Strategic Action Plan (2002)
DC Streetcars (may run down M Street SE someday)

Capitol Gateway and Southeast Federal Center Zoning Overlays
Two documents that spell out in extreme detail exactly what the requirements are for developments along South Capitol, M, in the Ballpark District, and at "The Yards". Read also my short explanatory treatise on these two overlays.

Pre-Redevelopment Media Overviews:
A Transformed Neighborhood Awaits Stadium (WP, 8/15/05)
      includes huge map of development plans
The Morphing of a Forgotten Neighborhood (WP, 9/2/2004)
      A brilliant take on the neighborhood!
Betting Big on Near Southeast (WP, 7/15/04)
Hope for the Waterfront (WBJ, 01)
Seeking a Better View On the Waterfront (WP, 3/8/98)
 

DC Government
Mayor's Office
Planning/Economic Development
   Office of Planning
DC Consumer & Regulatory Agency
DC Office of Zoning
DC Municipal Regulations | Zoning
DC Dept. of Transportation

DC City Council
Tommy Wells

ANCs: 6D | 6B
David Garber (6D07)
Kirsten Oldenburg (6B04)
Police: MPD-1D | PSA 105

Other Organizations
National Capital Planning Commission
Earth Conservation Corps
Capitol Hill Restoration Society
Barracks Row Main Street
Marines Community Integrated Master Plan
 

 

News Publications
The Hill Rag
The Southwester

Other DC Neighborhood/City Blogs
SW DC - The Little Quadrant That Could
The Hill is Home
Congress Heights on the Rise
Greater Greater Washington
WashCycle
Penn Quarter Living
Frozen Tropics
The Triangle
14th and You
The 42
Beyond DC
Richard Layman
 




Top of Page | Contact JD | Advertise on JDLand
Near Southeast RSS Feed

© Copyright 2014 JD.
All photos © Copyright JD - See information on photo uses, licensing and purchasing.