Barracks sketch from the Draft Framework.
New Marine Barracks

In 1999, the DC Housing Authority transferred to the Department of the Navy approximately six acres of the Arthur Capper Dwellings site at 7th and K Streets, SE, for the development of Bachelor Enlisted Quarters, parking, personnel support and recreational facilities.

Links:
1999 Acquisition/Development Plan (NCPC)
(everything you ever wanted to know!)
Marine Barracks Home Page


Looking at the BEQ's southern facade, along L Street, from the roof of the old Capper Seniors building. The dome of the Library of Congress is at upper left; the US Capitol dome is just out of frame. (11/1/07) 



The new barracks under construction, looking at the same angle (the northwest corner of 7th and L streets, SE) as in the rendering at the top of the page. (05/03)


Finished. (11/05)



Looking southeast from Virginia Avenue at the barracks construction, with the Capper Senior apartment building in the background. (06/03)


Fourteen months later, both the BEQ and the parking garage are completed, seen here from 5th and Virginia in November 2004, during the brief time between the demolition of the Capper Apartment building and the start of construction on Capper Seniors #1. (11/04)



Another view of the barracks construction along the north side of L Street,
this time looking from 5th Street. (05/03)


Almost there.... (07/04)



Looking west into the barracks construction area from 7th Street,
just south of its intersection with Virginia Avenue. The driveway is actually K Street (which will not be reopened), and the now-demolished Capper Apartment buildings at the far right. (05/03)


The same location, more than two years later. If you have very sharp eyes, you can see the construction of the new Capper Seniors #1, and even Capitol Hill Tower in the distance. (10/05)



Looking south on 7th Street from Virginia Avenue, through the intersection with K Street, early on in construction, in January 2003. The Arthur Capper Seniors building at 7th and M is at rear. (01/03)


The eastern edge of the BEQ, on 7th Street, at the completion of construction in August 2004. (08/04)


News Items Posted For This Project      (Get All Latest Near Southeast News via RSS, E-Mail)

This Week's Events: Lower 8th Visioning, Marine Barracks, ANCs 6B and 6D (and Trapeze School?)
(2/22/10 8:27 PM)

A few items on the agenda this week, should you choose to accept any or all of these missions:
* The Lower 8th Street Visioning Process is having its final public meetings on Tuesday (Feb. 23) at 8:30 am and 7 pm at the People's Church, 535 8th St., SE. In case you haven't been following along, here's a good description by Barracks Row Main Street of what the process has been and hopes to achieve (via The Hill is Home): "The Lower 8th Street SE Visioning Process Advisory Committee has coordinated a vision process with property owners, other community stakeholders, and Barracks Row Main Street along the Lower 8th Street, SE corridor. Sponsored by the Capitol Riverfront BID, this process is an attempt to gain consensus on a vision for the area and to address issues of height, density, mix of uses, parking and access, as well as what should be the character of a redesigned Virginia Avenue Park as an amenity or community benefit for the Capitol Riverfront neighborhood and Capitol Hill. If consensus can be reached on the vision, it could serve as the basis for asking the Office of Planning to develop a small area neighborhood plan that could then be used as justification for any agreed upon zoning or density changes. This final meeting will attempt to synthesize a community consensus on the vision of Lower 8th Street." (A lot of qualified statements in there.)
* Alas, at the same time as the 8th Street evening session is the rescheduled ANC 6B monthly meeting, at 7 pm at the Old Naval Hospital at 921 Pennsylvania Ave., SE.
* Also via The Hill is Home, news that the first community workshop on the Marines' "Community Integrated Master Plan" as they look for a new location for their barracks and other facility needs is scheduled for Wednesday (Feb. 24) from 6 to 8 pm at the Van Ness Elementary School at 5th and M, SE. This first workshop "will focus on the goals and objectives" of the CIMP, according to the project's web site.
* On Thursday, Feb. 25, ANC 6D is having its snow-postponed monthly meeting, at St. Augustine's church at 6th and M, SW, at 7 pm.
* The Trapeze School posted on its Facebook page this afternoon that they're getting their inspections on Tuesday, and are hoping to have their first classes in their new home at Fourth and Tingey at the Yards on Thursday.

More Details on the Marines' Space Needs
(2/1/10 6:54 PM)

Voice of the Hill has just posted an informative article giving a lot more detail on the Marine Corps' plans to replace the aging barracks building "20" on the north side of the freeway at Eighth and I, along with their desire to build additional facilities, including a fire station, child development center, gym, pool, parking, meeting space, post office, basketball and tennis courts, an indoor parade field, and a new Marine Barracks Washington museum. All in all, the Marines are looking for 173,000 square feet of space, some of which would be accessible (they say) to Hill residents.
Possible locations they're looking at for the new barracks appear to be north of the freeway (and outside of my boundaries!), including the Potomac Gardens public housing project at 12th and G, SE, and the Tyler Elementary baseball field at 10th and I, SE, but they are also considering the Marine Corps Institute site within the Washington Navy Yard. Also shown on their maps as a possible site is Square 882 (across from the barracks annex built in 2004), currently Nats Parking lot W on the site of the old Capper Seniors building, but the Voice article says that the DC Housing Authority has taken that block off the table--I've been hearing that DCHA is close to securing financing for the mixed-income apartment building they intend to build on the north side of that block, and would possibly begin construction by the end of this year.
The article also says that the current owners of the Blue Castle, Madison Marquette, have expressed an interest in leasing space in the old trolley barn to the Marines.
The Marines' web site for the development project has been updated with the packet from last week's open house, an FAQ, and other materials. There apparently will be a series of community meetings, which are described by the FAQ thusly: "The current plan is for the first workshop (February) to focus on needs and goals, the second workshop (March) to focus on potential development sites, the third workshop (April) to focus on CIMP alternatives, and the fourth workshop (May) to focus on CIMP consensus elements. Additionally, a charrette focused on the CIMP way forward will be held in fall 2010." (If you're interested in these, you should plan to attend rather than waiting for a JDLand report--I tend to stay away from community meetings that are pure planning sessions, because, well, they drive me insane.)
And note that this is a *different* armed forces expansion plan from the one we heard about last week, where the Navy is looking for additional office space outside of the walls of the Navy Yard. Got to keep your service branches straight these days!
Comments (9)

Tidbits From the Past Few Days (Foreclosure, Marines, WMATA Cuts, 11th Street Bridges, 1015 Half)
(1/21/10 10:35 AM)

Rounding up some new and Tweeted tidbits, now that I've recovered from cranking out the State of the Hood:
* (h/t "reader X") The second foreclosure sale held yesterday for the boarded-up apartment building and surrounding lots at Potomac, Ninth and L brought no bids above the $2 million starting point, so the properties will now return to the lender. An earlier auction back in October had brought a $2.461 million winning bid, but that deal fell through. The properties were originally bought by ICP Partners in 2006, along with the gray building at Eighth and Potomac, for $9 million.
* Via ANC 6B03 commissioner Norm Metzger, the Marines have created a web site for their "Community Integrated Master Plan." The site describes this planning process as evaluating "community-military development partnering options" because "[t]here are unmet facility needs and security requirements at Marine Barracks Washington and a potential to meet common community and military needs through the process" and that their goal is "to use a coordinated planning process to create a win-win in meeting the development needs of the local community and Marine Corps." Now that that's cleared up, you can go to the open house they're having on Jan. 27 from 5 to 8 pm in the North Hall of Eastern Market, to "assist the planning team in identifying issues, concerns, and potential opportunities for military-community development partnering."
* One of many service reductions proposed by WMATA to help close their FY2010 budget gap is to shut down one of the two entrances to the Navy Yard metro station on weekends. (They don't say which one.) The public hearing on their various proposals is Jan. 27 at 5:30 pm. UPDATE: From Michael Perkins, in the comments, it would be the west entrance, at Half and M. I wonder if this would only be when there are no stadium events?
* Via the Capitol Hill Chamber of Commerce's Twitter feed, there will apparently be one more Lower 8th Street visioning session, on February 22. After this final session, the group will forward its recommendations to the Office of Planning on what sort of development should be emphasized for these blocks south of the freeway.
* In Sunday's Post, Dr. Gridlock took a look at the 11th Street Bridges project, telling drivers what to expect as the construction unfolds, and that the "new bridges will forge a link between Maryland, the District and Virginia that has been missing since the original highway plan for the District was abandoned decades ago. And it will create a new link between neighborhoods on both sides of the Anacostia while relieving them of some of the commuter traffic that spills onto local streets."
* As part of the start of work on the bridges, a raze permit application has been filed to demolish the old red brick buildings between the current bridges that housed the Anacostia Community Boathouse, whose operations are now moving up-river to a temporary (maybe permanent) home at the Anacostia Marina.
* A little time spent trolling through public records shows that within the past month a bunch of the liens brought against Opus East when they liquidated and stopped work on 1015 Half Street have been settled. No indications from the new owner (Douglas Wilson Companies) as to when construction might restart, despite their statements back in October that it would be happening soon.

Final Approval for Capper Zoning Changes; More Info on Security Requirements at 7th and M
(6/9/09 3:34 PM)

Last night the Zoning Commission voted 3-0-2 to give final approval to the Capper zoning requests that have been wandering through the system for nearly a year. The record was reopened to add correspondence between the developer (Capper-Carrollsburg Ventures LLC, which includes the DC Housing Authority), the Marines, and the Navy Yard in reference to security concerns both service branches have about 90-foot buildings being constructed on the site of the old Capper Seniors building at Seventh and M. (Read more about the concerns here.)
The National Capital Planning Commission documents I linked to last week included letters sent by the Marines and the Navy in early April setting out their objections; the NCPC has now posted new letters from the Navy and also Holland and Knight (representing the developers), laying out the wording of the agreement between the parties to install (at the services' expense) surveillance cameras on the top of both the new office building that faces the Navy Yard and the new apartment building that faces the Marine Bachelor Enlisted Quarters, and that the developer will provide to the Navy Yard a list of tenants on the fourth through eighth floors of the office building, though "this provision shall not be deemed to grant the Navy any right to approve or disapprove of any tenants in the office building." There's also a requirement to notify the Navy and Marines about any events to be held on the roof decks of the buildings, but "for informational purposes only," without requiring any type of approval. With the Navy agreeing to the wording of this agreement, its objection to the zoning case was withdrawn.
I'll note that there's also reference in these letters to a June 3 letter from the Marines that is not included in the document packet, which seems to indicate that the Marines did not agree to the wording despite the developer's having believed that there had been an agreement. Quoting (see page 9): "In fact, nothing in the Marines' June 3rd letter indicates why the Applicant's proposed conditions are unacceptable, or what remaining concerns the Marines have." There's then this sentence, which seems to be hinting at plans by the Marines for some new development: "The Marines, beyond the scope of the proposed modifications which are the subject of this pending application, have requested a delay to accommodate their entirely new planning initiative." And what would this new planning initiative be? I'm hearing murmurs that the Marines may be looking for more land for more barracks, though I'm not able to confirm that.
In any event, the developer laid out a list of reasons that this zoning approval should not be delayed, and both the NCPC (last week) and the Zoning Commission (last night) gave their approvals for the zoning changes in spite of whatever objections the Marines were putting forth.
There wasn't much discussion of all of this at the Zoning Commission's meeting, but I need an excuse to link to the Video on Demand section of the DCOZ web site, which apparently has been around for months but which I only noticed last night. So, if you want to watch this or any ZC/BZA public meeting going back to November of 2008, they're now there for the taking. (And it's also nice to see how quickly last night's video was posted.)
Now, with these Capper zoning changes approved, the next milestone to watch for will be when the Housing Authority can find financing for another PILOT bond offering to rebuild the infrastructure on the west side of the Capper footprint (including around Canal Park), as well as the mitigation and demolition of the trash transfer station at New Jersey and K. That PILOT financing will also fund the Community Center that has been the subject of much contentious back-and-forth. Are the credit markets unfrozen enough to get this PILOT off the ground? We shall see....
Comments (0)
Blog Tags: capper, 600m, navyyard, barracks

Navy/Marines Concerned About Buildings at 7th and M
(6/3/09 1:02 PM)

Contained in the materials for Thursday's meeting of the National Capital Planning Commission is a document that sheds some light on something I've always wondered about--exactly how does the Navy Yard feel about the planned 90-foot-tall office building right across the street at 600 M, on the site of the old Capper Seniors building? And, concurrently, how do the Marines feel about the planned apartments directly between this new 600 M building and the Marine Bachelor Enlisted Quarters on L Street?
The NCPC board is reviewing the Zoning Commission's approval of the slew of Capper zoning changes that I wrote so much about earlier this year, some of which focus on these two new buildings on the old Capper Seniors site. The Executive Director's recommendation document (which provides some good background if you haven't been following along), refers to letters included in the document to the Zoning Commission from both the Navy and Marines stating that the new buildings on what's known as Square 882 "may pose a safety and security threat to the military personnel at both the Navy Yard and the Marine Barracks and that the there will be a visual impact on the Navy Yard Historic District."
Apparently the Navy, Marines, the DC Housing Authority, and Forest City (developers of 600 M) have tentatively agreed to a few steps to mitigate these concerns: the placement of surveillance cameras on the roofs of the proposed buildings, procedures for notifying the Navy and Marines when the roofs are to be accessed, review by the Marines and Navy Yard of tenants wishing to occupy the third through eighth floors of the 600 M office building, and a "window design to enhance security for Navy and Marines." (On this last point, the document says that "the Navy and Marines would request that the windows facing their sites not be operational," but I wonder how tenants in the proposed apartment building along L Street would feel if none of their windows could ever be opened.) The document says that memorandums of understanding between the housing authority and the Navy and the Marines should be able to be completed within the next few weeks.
Additionally, in its letter to the Zoning Commission, the Navy Yard mentions its belief that "buildings exceeding the currently permitted fifty (50) foot height restrictions located across M Street from the Navy Yard Historic District will negatively impact the view shed from the Navy Yard" and "could potentially compromise the integrity of the Washington Navy Yard Historic District, including the Latrobe Gate." It might be worth noting here that the old Capper Seniors building, built in the 1950s and demolished in 2007, was nine stories high, and so an uninterrupted "view shed" is not something that the Navy Yard has always enjoyed since its arrival in the neighborhood back in 1799.
The NCPC's reason for reviewing Zoning Commission cases in DC is to determine whether the proposed actions would have an "adverse effect" on federal interests, and, in this case, the NCPC staff is advising their commission to vote to advise the Zoning Commission that these Capper cases do indeed meet that "adverse effect" standard. Also, the NCPC staff is recommending that the Zoning Commission delay their final action on this case (scheduled for Monday, June 8) to allow the agreement described above to be finalized.
Comments (11)
Blog Tags: capper, 600m, navyyard, barracks

Capitol Quarter Houses on the Market; Sunday Concert at Marine Barracks Annex
(2/5/09 9:21 PM)

Two small tidbits:
* EYA sent out an e-mail today announcing that they are releasing "the final townhomes in Phase 1" at Capitol Quarter, with prices starting from the $630s. I don't know how many units are in this batch, or where in the Phase I blocks they're located. I'm pretty sure that a while back Phase 1 was billed as "sold out"--if I'm correct, these would be some houses originally reserved but now back on the market. (Buyer decides not to buy, buyer's credit worthiness tanks, etc. etc.)
UPDATE, 2/7: EYA tells me that the houses released are spread throughout the development: 421 L Street, under construction and expected to be ready in April (listed for $720,340 on the EYA "Move In Now" list), two houses in the block just to the north (expected to be ready in the fall), and four houses in the block bounded by I/Virginia, Fifth, Fourth, and K that could be ready by the end of the year. On all of these blocks the reservations placed by homeowners over the past few years have now been converted to contracts; that is expected to happen for the final Phase 1 block (between Third and Fourth and Virginia and I) later this year.
* From the Post calendar listings, word of a concert on Sunday Feb. 8 at the Marine Bachelor Enlisted Quarters. (This is the first time I've ever heard of a concert there, though it's more than possible that the news of previous ones didn't make it onto my radar.) Here's the particulars: "MARINE CHAMBER ENSEMBLE, performance of works by Libby Larsen, Telemann and Stravinsky; followed by a tour of the facility; light refreshments served. 2 p.m., Marine Barracks Annex, John Philip Sousa Band Hall, Seventh Street and Virginia Avenue SE. Free. 202-433-4011." (hat tip to reader S.)
Comments (6)
Blog Tags: capper, capquarter, barracks


Near Southeast DC Home Page
Top of Page | RSS Feed | Contact JD
Advertise on JDLand.com

© Copyright 2010 JD.
All photos © Copyright JD - See information on photo uses, licensing and purchasing.

  

More Near Southeast
Home Page
Contact JD
About This Site
Advertise on JDLand
E-Mail Updates
Upcoming Events
Bus and Rail Times


RSS and Other Web 2.0 Feed Options

Feedburner Subscribers
JDLand.com on Twitter
JDLand.com on Facebook