The DC Housing Authority has filed a request with the Zoning Commission for a time extension to construct the mixed-income apartment buildings it has planned for the north half of Square 882 (the old Capper Seniors block along L Street between 5th and 7th, seen at right) and the north half of Square 769, between 2nd and 3rd on L just east of Canal Park (below, the building at left, next to the proposed 250 M Street).
When the plans for these two buildings were approved by the Zoning Commission in 2009 (see the zoning order), it was required that building permits be applied for by August of this year, with construction to begin by August of 2012. However, attempts at funding either the Square 882 189-unit building or 171-unit Square 769N building the have not thus far borne any fruit, and so a time extension is needed. Between them, the buildings would have 72 units reserved for households making less than 60 percent of the area median income, and the Square 769 building would also have just over 4,000 square feet of ground-floor retail space.
The Zoning Commission will hear this request at its meeting on Monday night; because there is no request to modify any portion of the PUD beyond the time requirement, this will most likely be handled as a consent calendar item. There will also be a presentation on this request and the state of the Capper redevelopment in general at Monday's ANC 6D meeting. (There was also one given at Tuesday night's ANC 6B's Planning and Zoning Committee meeting, but I had a baseball game to watch.) But since the Zoning Commission hearing is at the same time as the 6D meeting, it would seem that there is no anticipated opposition from 6D.
The Office of Planning prepared a short report recommending approval of the time extension, showing that the requirements for an extension have been met. It also quotes the development team as saying that there have been 75 outreach efforts for financing, all unsuccessful. "The inability to secure financing for residential projects, especially those including affordable units, is not unusual in the current marketplace."
If you want to know more about these two planned apartment projects, and the other three mixed-income buildings planned along the east side of Canal Park and on the DPW/trash transfer site, my Capper Apartments page has additional background, as do the scads of blog posts I've written on the various plans. And my main Capper page has the background on the entire redevelopment project.
UPDATE: And, of course, within seconds of my pulling the trigger and posting this entry, I've received a copy of the letter to the Zoning Commission requesting the PUD. Which I'm posting before reading.
Comments (2)
 
 More About Lofts at Capitol Quarter

JDLand.com Home

Comments

B in DC says: (9/7/11 3:36 PM)
Just throwing out a random question. What would be the possibility of turning the four remaining parcels over to EYA, allowing them to develop "Phase 3" of Capitol Quarter, but with a greater percentage of affordable units to still provide for replacements for all former Capper residents? EYA/DCHA might have a better chance of getting funding that way.


JD says: (9/7/11 3:43 PM)
I think there are all manner of possibilities being explored. But you wouldn't be able to get the density required to get all needed affordable housing units (and the needed number of market-rate units to make the projects financially viable) by just replacing the apartment buildings with townhouses. There are 1130 units still on the boards to be constructed (excluding Capitol Quarter), of which 309 need to be public housing. You have to build apartment buildings to get to those numbers.




Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
jmauro on Southeast Blvd.: None of the new options will work. They all ignore the fact that the CSX railw...
Packinblackandred on Southeast Blvd.: Awesome news, glad to hear it!
JD on Southeast Blvd.: (Laziness note: I appear to have successfully made it through my latest surgery,...
E. Masquinongy on Southeast Blvd.: I wonder about the wisdom of DDOT administering this development. This is an imm...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
M ST SE AND HALF ST SE   ROBBERY /  08/17/14
800 B/O VIRGINIA AVE SE   THEFT F/AUTO /  08/17/14
M ST SE AND 5TH ST SE   THEFT F/AUTO /  08/15/14
1400 B/O 1ST ST SE   THEFT F/AUTO /  08/14/14
1000 B/O 1ST ST SE   BURGLARY /  08/12/14
800 B/O L ST SE   THEFT F/AUTO /  08/11/14
HALF ST SE AND L ST SE   THEFT F/AUTO /  08/11/14
1000 B/O NEW JERSEY AVE SE   THEFT /  08/07/14
1100 B/O 10TH ST SE   THEFT /  08/07/14
70 B/O I ST SE   THEFT /  08/02/14
100 B/O K ST SE   THEFT F/AUTO /  08/01/14
200 B/O L ST SE   THEFT F/AUTO /  07/30/14
L ST SE AND 2ND ST SE   THEFT F/AUTO /  07/30/14
70 B/O I ST SE   MOTOR VEHICLE THEFT /  07/29/14
70 B/O I ST SE   THEFT /  07/29/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
08/11/14 
TOLL DC LP / ALBERT J. PEARCE
FB1400108 / SUPPLEMENTAL
1259 1ST ST SE   
08/11/14 
CAPITAL RIVERFRONT HOTEL LLC / CAPITAL RIVERFR HOTEL LLC
AH1400636 / CONSTRUCTION
AFTER HOURS FOR PERMIT NUMBER B1401471 FOR 8 / 12 THROUGH 9 / 11 FROM 5AM TO 7PM MONDAY THROUGH SATURDAY.
1201 4TH ST SE   
08/12/14 
JBG/FEDERAL CENTER LIC / JIM CALABRESE
AN1400129 / CONSTRUCTION
PLEASE EXTEND PERMIT AN1300174 THIS IS THE FIRST EXTENSION AND PERMIT WILL BE VALID UNTIL 1 / 31 / 2015.
1212 4TH ST SE   
08/25/14 
FC 1212 LLC / MARK E. RESNICK
E1408462 / SUPPLEMENTAL
1331 4TH ST SE   
08/14/14 
F. C. 1331 LLC / FVI 2020
B1402843 / CONSTRUCTION
CONSTRUCTION OF A BRAND NEW 11 STORY BUILDING. THE BUILDING IN TOTAL IS 350 000 SQ FT. ADDING 327 RESIDENTIAL RENTAL UNITS 20 000 SQ FT. IN COMMERCIAL SPACE AND 3 BELOW GRADE PARKING LEVELS.
   
08/15/14 
CLARK CONCRETE
AH1400650 / CONSTRUCTION
AFTER HOURS TO POUR CONCRETE ON JOBSITE FROM 7AM TO 7PM FROM SUNDAY TO SATURDAY 8 / 15 / 2014 TO 11 / 15 / 2014
1000 5TH ST SE   
08/13/14 
UNITED STATES OF AMERICA /
FD1400132 / CONSTRUCTION
NEW FOUNDATION TO GRADE PERMIT FOR NEW COMMUNITY CENTER INCLUDING UTILITIES. REVISION TO FD1400029 TO REVISE STRUCTURAL DETAILS OF COLUMS.
   
08/20/14 
UNITED STATES OF AMERICA / BRUCE G. PICKETT
E1408304 / SUPPLEMENTAL
1220 12TH ST SE   
08/27/14 
FAIRBANKS MORSE ENGINE / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1411219 / CONSTRUCTION
INTERIOR ONLY NON-STRUCTURAL ALTERATION TO EXISTING OFFICE SPACE. WORK INCLUDS MINOR PARTITION CHANGES AND THE ASSOCIATED HVAC AND ELECTRICAL ALTERATIONS.
1015 HALF ST SE   
08/12/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
TL1400162 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 1ST FLOOR PERFORMANCE STUDIO SPACE AND OFFICE SPACE. PARTITIONS FURNITURE MECHANICAL ELECTRICAL AND LIFE SAFETY. CBS
   
08/15/14 
HALF ST SE LLC / ROBERT L HUNTER
M1402951 / SUPPLEMENTAL
   
08/16/14 
SAM HOLLEN / DONALD VEALS; SAM HOLLEN; DONALD VEALS
E83010192 / SUPPLEMENTAL
200 I ST SE   
08/08/14 
DANIEL RILEY / OMAR BIAGAS; DANIEL RILEY; JOHN BIAGAS
E47247428 / SUPPLEMENTAL
41 L ST SE   
08/20/14 
WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY (WMATA) / SAMIR ALQUTRI - GEOTECHNICAL SOLUTIONS INC.
SB1400402 / CONSTRUCTION
GSI PLANS TO DRILL 4 SOIL TEST BORINGS TO CONFIRM SOIL STRENGTH WITH A HOLLOW-STEM AUGER EQUIPPED WITH A SPLIT SPOON SAMPLER FOR THE SPT N-VALUE TESTS DOWN TO A MAXIMUM DEPTH OF 80 FEET BELOW EXISTING GRADES. ALL BORINGS WILL BE DRILLED TO THE MAXIMUM DEPTH OR AUGER REFUSAL WHICHEVER OCCURS FIRST. THE BORE HOLES DIMENSION WILL BE 3.25 INCHES AND SHALL BE GROUTED UPON COMPLETION.
20 M ST SE   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
P96600069 / SUPPLEMENTAL
   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
G22130990 / SUPPLEMENTAL
   
08/25/14 
SUBWAY / N/A; DAMON ELLIS
SG1400416 / CONSTRUCTION
INSTALLATION OF NON ELECTRIC SIGN 10FT 8IN LENGTH 2IN WIDE 25IN HEIGHT
   
08/27/14 
JOHN GLUSEPPE-RAMCO / CARL LAVENDT; JOHN GLUSEPPE-RAMCO; CARL LAVENDT
E10905761 / SUPPLEMENTAL
100 M ST SE   
08/16/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
901 M ST SE   
08/14/14 
CARLTON RAY
AH1400642 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
08/14/14 
CARLTON RAY
AH1400641 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
861 NEW JERSEY AVE SE   
08/21/14 
CONSOLIDATED RAIL CORPORATION / ROBERT COLISH
P1407975 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
08/12/14 
NJA ASSOCIATES LLC / COLIN CLARK
B1308085 / CONSTRUCTION
CONSTRUCT A NEW 13 STORY APARTMENT BUILDING WITH THREE BELOW GRADE PARKING LEVELS FIRST FLOOR RETAIL A PRIVATE SWIMMING POOL PROJECTIONS OF BAY WINDOWS 324 UNITS TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND ELEVATOR WORK.
1200 SOUTH CAPITOL ST SE   
08/26/14 
MR BALLPARK 4 LLC. / MR BALLPARK 4 LLC.; RPS INC.
SB1400375 / CONSTRUCTION
ENVIRONMENTAL SOIL BORINGS FOR DUE DILIGENCE INVESTIGATION. ADVANCE A SERIES OF 10 ENVIRONMENTAL SOIL BORINGS AT THE SUBJECT SITE TO COLLECT SOIL AND GROUNDWATER SAMPLES FOR FIELD SCREENING AND LABORATORY ANALYSIS. THE SOIL BORINGS ARE BEING CONDUCTED AS PART OF A DUE DILIGENCE INVESTIGATION ASSOCIATED WITH A REAL ESTATE TRANSACTION. INVESTIGATION DERIVED WASTE -IDW- WILL BE LABORATORY TESTED AND ...
1230 SOUTH CAPITOL ST SE   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / RAYMOND SCIANNELLA
E1408379 / SUPPLEMENTAL
   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / CHRIS WING
B1410888 / CONSTRUCTION
INTERIOR ALTERATION TO EXISTING SELF STORAGE BUILDING TO REPLACE FIRE ALARM SYSTEM.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.