The DC Housing Authority has filed a request with the Zoning Commission for a time extension to construct the mixed-income apartment buildings it has planned for the north half of Square 882 (the old Capper Seniors block along L Street between 5th and 7th, seen at right) and the north half of Square 769, between 2nd and 3rd on L just east of Canal Park (below, the building at left, next to the proposed 250 M Street).
When the plans for these two buildings were approved by the Zoning Commission in 2009 (see the zoning order), it was required that building permits be applied for by August of this year, with construction to begin by August of 2012. However, attempts at funding either the Square 882 189-unit building or 171-unit Square 769N building the have not thus far borne any fruit, and so a time extension is needed. Between them, the buildings would have 72 units reserved for households making less than 60 percent of the area median income, and the Square 769 building would also have just over 4,000 square feet of ground-floor retail space.
The Zoning Commission will hear this request at its meeting on Monday night; because there is no request to modify any portion of the PUD beyond the time requirement, this will most likely be handled as a consent calendar item. There will also be a presentation on this request and the state of the Capper redevelopment in general at Monday's ANC 6D meeting. (There was also one given at Tuesday night's ANC 6B's Planning and Zoning Committee meeting, but I had a baseball game to watch.) But since the Zoning Commission hearing is at the same time as the 6D meeting, it would seem that there is no anticipated opposition from 6D.
The Office of Planning prepared a short report recommending approval of the time extension, showing that the requirements for an extension have been met. It also quotes the development team as saying that there have been 75 outreach efforts for financing, all unsuccessful. "The inability to secure financing for residential projects, especially those including affordable units, is not unusual in the current marketplace."
If you want to know more about these two planned apartment projects, and the other three mixed-income buildings planned along the east side of Canal Park and on the DPW/trash transfer site, my Capper Apartments page has additional background, as do the scads of blog posts I've written on the various plans. And my main Capper page has the background on the entire redevelopment project.
UPDATE: And, of course, within seconds of my pulling the trigger and posting this entry, I've received a copy of the letter to the Zoning Commission requesting the PUD. Which I'm posting before reading.
Comments (2)
 
 More About Lofts at Capitol Quarter

JDLand.com Home

Comments

B in DC says: (9/7/11 3:36 PM)
Just throwing out a random question. What would be the possibility of turning the four remaining parcels over to EYA, allowing them to develop "Phase 3" of Capitol Quarter, but with a greater percentage of affordable units to still provide for replacements for all former Capper residents? EYA/DCHA might have a better chance of getting funding that way.


JD says: (9/7/11 3:43 PM)
I think there are all manner of possibilities being explored. But you wouldn't be able to get the density required to get all needed affordable housing units (and the needed number of market-rate units to make the projects financially viable) by just replacing the apartment buildings with townhouses. There are 1130 units still on the boards to be constructed (excluding Capitol Quarter), of which 309 need to be public housing. You have to build apartment buildings to get to those numbers.




Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
Jaybird on Details on The: "Speak softly, and carry a big stick."
ValveetaChz on Arris and Lofts/Capitol: I agree with JES. I am in love with the renderings of Arris and can't wait to se...
conngs0 on Details on The: I'm excited to try the place out whenever it opens. And I give Mr. Ross credit ...
JES on Arris and Lofts/Capitol: I don't know what it is, but I still just love the Arris architectural design. C...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 1ST ST SE   THEFT
 11/21/14
900 B/O 5TH ST SE   BURGLARY
 11/21/14
200 B/O I ST SE   THEFT
 11/21/14
1200 B/O NEW JERSEY AVE SE   THEFT
 11/20/14
900 B/O NEW JERSEY AVE SE   THEFT F/AUTO
 11/17/14
700 B/O L ST SE   THEFT
 11/16/14
300 B/O I ST SE   ASSAULT W/DANGEROUS WEAPON
 11/15/14
4TH & TINGEY ST SE   THEFT
 11/13/14
UNIT B/O K ST SE   THEFT F/AUTO
 11/12/14
100 B/O M ST SE   THEFT
 11/10/14
200 B/O VIRGINIA AVE SE   ROBBERY
 11/09/14
900 B/O M ST SE   THEFT F/AUTO
 11/09/14
9TH & L ST SE   THEFT F/AUTO
 11/07/14
11TH & M ST SE   THEFT F/AUTO
 11/07/14
100 B/O K ST SE   THEFT F/AUTO
 11/07/14
1000 B/O 4TH ST SE   THEFT F/AUTO
 11/07/14
50 B/O M ST SE   THEFT
 11/05/14
400 B/O K ST SE   THEFT F/AUTO
 11/03/14
1100 B/O NEW JERSEY AVE SE   THEFT F/AUTO
 10/29/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15

Recent Issued Building Permits Archive  
1277 1ST ST SE   
11/21/14 
BALLPARK SQUARE LLC A DELAWARE LLC / DENNIS CONSULTING
SH1400051 / CONSTRUCTION
EROSION & SEDIMENT CONTROL SITE PERIMETER CONTROL EXCAVATION SHEETING & SHORING AND ASSOCIATED UTILITIES.
1331 2ND ST SE   
11/13/14 
DC WATER
SB1400419 / CONSTRUCTION
TYPE OF WELL(S):OBSERVATION WELLS INCLINOMETERS VW PIEZOMETERS AND EXTENSOMETERS FOR UPGRADE OF DC WATER CLEAN RIVERS PROJECT DIVISION I. NUMBER OF WELL(S):112. DEPTH OF WELL(S):UP TO 60 FT. DIAMETER OF WELL(S): 6". DRILLING METHOD: CASED AND HSA. PLEASE SEE THE ATTACHED WORKPLAN.
1331 4TH ST SE   
11/26/14 
UNITED STATES OF AMERICA / DONALD V. ELLENBERGER
M1500519 / SUPPLEMENTAL
1000 5TH ST SE   
11/25/14 
UNITED STATES OF AMERICA / JOSEPH M MAGNOLIA
P1501521 / SUPPLEMENTAL
200 I ST SE   
11/24/14 
HASSAN DEPT. OF GENERAL SERVICES
PC24903284 / POST CARD
INTERIOR DEMOLITION OF NON-BEARING ELEMENTS IN A SPACE UP TO 5 000 SQUARE FEET (464.5 SQUARE METERS)
   
11/24/14 
DEPT OF GENERAL SERVICES DC / DEPT OF GENERAL DC
PC43136454 / POST CARD
INSTALLATION OF NOT MORE THAN 10 NEW OUTLETS AND NOT MORE THAN 10 NEW LIGHTING FIXTURES FOR A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
332 K ST SE   
11/10/14 
KRISTIN L HENRIKSON / JOHN A. TETI
E1501053 / SUPPLEMENTAL
80 M ST SE   
11/12/14 
WELLS REIT II 80 M STREET LLC / RONNIE E WRIGHT
E1501089 / SUPPLEMENTAL
20 M ST SE   
11/21/14 
SOUTH EAST REALTY LLC SOUTH EAST REALTY LLC / ADOLPHUS SIMMONS; SOUTH EAST REAL SOUTH EAST REALTY LLC; ADOLPHUS SIMMONS
P92093458 / SUPPLEMENTAL
80 M ST SE   
11/21/14 
VEIC EXPANSION / DAVID RAINE; VEIC EXPANSION; DAVID RAINE
P77248641 / SUPPLEMENTAL
   
11/22/14 
NICHOLAS DODD / NICHOLAS DODD; NICHOLAS DODD; NICHOLAS DODD
E45845237 / SUPPLEMENTAL
901 M ST SE   
11/13/14 
CARLTON RAY
AH1500084 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
11/13/14 
CARLTON RAY
AH1500085 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
75 N ST SE   
11/26/14 
CRANE SERVICE CO / CHRISTINE LONG
AH1500133 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 2:00AM THRU 11:59PM
801 NEW JERSEY AVE SE   
11/12/14 
GREYSTAR / JOHN MORIARTY AND ASSOC.
F1500068 / CONSTRUCTION
INSTALL A TEMPORARY CONSTRUCTION SITE FENCE ON PRIVATE PROPERTY. FENCE TO BE 6' HIGH ON BLOCK SUPPORTS.
880 NEW JERSEY AVE SE   
11/19/14 
880 NEW JERSEY AVENUE LLC / OTIS ELEVATOR COMPANY
EN1500172 / SHOP DRAWING
TYPE OF ELEVATOR : ONE (1) TRACTION / CENTRAL / VERTICAL TRANSPOTATION
   
11/20/14 
BAKER DC / CHRISTINE LONG
AH1500122 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 12:01 AM THRU11:59 PM
1100 NEW JERSEY AVE SE   
11/10/14 
SQUARE 742 LLC / ELMUBARK E. ELNAHAS
E1501060 / SUPPLEMENTAL
125 O ST SE   
11/14/14 
DISTRICT OF COLUMBIA FOREST CITY WASHINGTON / JOPATRIC AMERICODE
SB1400418 / CONSTRUCTION
EIGHT SOIL BORINGS ON PRIVATE PROPERTY. FOREST CITY F1 BLOCK CINEMA BORINGS SHALL BE 10 INCH DIAMETER MUD ROTARY METHOD; 2 SHALL BE DRILLED TO A DEPTH OF 100 FEET AND 6 TO A DEPTH OF 60 FEET; IF THE CONFINING UNIT IS ENCOUNTERED DURING DRILLING THEN ADVANCEMENT OF THE AUGERS SHOULD BE HALTED AND THE PERMANENT OUTER CASING SHOULD BE SET INTO 10 FEET (IF THE CONFINING UNIT IS THINNER THAN 10FT OUTER...
25 POTOMAC AVE SE   
11/10/14 
BARR CONCRETE
TC1500004 / CONSTRUCTION
TOWERCRANE FOR JOBSITE USE
810 POTOMAC AVE SE   
11/26/14 
810 POTOMAC AVE SE HOLDINGS LLC
B1501997 / CONSTRUCTION
DEMO EXISTING WINDOWS AND REPLACE WITH NEW WINDOWS THAT COMPLY WITH HISTORIC PROPERTY REQUIREMENTS
921 POTOMAC AVE SE   
11/20/14 
PAUL A GHIOTTO / MURRAY LYONS
P1501384 / SUPPLEMENTAL
300 TINGEY ST SE   
11/24/14 
FC BOILERMAKER LLC / MATT LOSIGNOR
P1501478 / SUPPLEMENTAL
   
11/12/14 
FC BOILERMAKER LLC / FRED LATIMORE
E1501087 / SUPPLEMENTAL
   
11/22/14 
FC BOILERMAKER LLC / GREGORY BIRCKHEAD; FC BOILERMAKER LLC; MICHAEL BELL
E55526822 / SUPPLEMENTAL
401 TINGEY ST SE   
11/20/14 
FOREST CITY / FVI 2020
SB1500055 / CONSTRUCTION
EXTENSION TO WORK IN REFERENCE WITH PERMIT SB1200282. SECOND EXTENSION FROM 10.25.14 TO 4.25.15
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
CUSHING PL   09/11/14
$ 9,000,000
HALF STREET RESIDENTIAL PJV LLC
 
HALF ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
CUSHING PL   09/11/14
$ 9,000,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
N ST   09/11/14
$ 12,500,000
HALF STREET RESIDENTIAL PJV LLC
 
HALF ST   09/11/14
$ 12,500,000
MR BP RESIDENTIAL #1A LLC
 
N ST   09/11/14
$ 12,500,000
MR BP RESIDENTIAL #1A LLC
 


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.