At Monday's ANC 6D meeting, Bryon Johnston of the 11th Street Bridges Project gave a presentation on the rebuilding of the bridges, including an overview of the design and its main features as well as an update on the construction progress. He was nice enough to pass along the slides, which may not mean quite as much without his narration but are still helpful for people who haven't been following along through the process.
A few parts of the new design on the Near Southeast side of the project are worth (re-)pointing out, if you can make it through my torrent of descriptions:
* The "freeway" traffic and the "local" traffic will now be separated, with four lanes inbound and four lanes outbound on the freeway/upriver bridge and two lanes inbound/outbound on the "local"/downriver bridge (which Johnston was referring to as "Local 11th Street" because 11th will now feel like a street that crosses a river), as shown on slide 10.
* The local bridge will allow easier access between Near Southeast and Anacostia, for not only cars but pedestrians and bicycles, as well as streetcars when the routes are expanded. As part of this, 11th Street south of M is going to become two-way, and there will be bike lanes in both directions on 11th north of the bridge. (Slide 9)
* Another feature that appears to be coming together for pedestrians and bicyclists is creating two overlooks that jut out above the river on the south side of the local bridge--these would use two of the in-water piers from the current downriver bridge, and you can see them at left and on slide 11.
* One of the big changes for traffic flow for both Near Southeast and Capitol Hill is that there is going to be a new two-lane on-ramp to go westward on the Southeast Freeway toward Virginia at 11th Street, underneath where the current flyover ramps are. (See slide 7.) Folks who have easier access to 11th Street will no longer have to drive along Virginia Avenue and/or 3rd Street to go westbound on the freeway.
But part of this new 11th Street intersection is that traffic coming from Pennsylvania Avenue along the sunken road that currently feeds directly into the freeway will instead be brought up to street level at this new signalized 11th Street intersection and will then drive straight onto the new on-ramp. So there will be some consternation from drivers using this route. (This is also shown on slide 7.)
* To go across the river from Near Southeast on the freeway bridge, for access to DC-295 northbound and I-295 southbound, drivers will have a new ramp on the southeast corner of 11th and M (slide 4). The existing ramp at 8th and Virginia will still be available, too.
* There will still be an exit ramp from the inbound freeway bridge to I Street, just as there is now (slide 4).
* If you look at slide 4 very closely (and/or click on the bird's-eye view at right) and follow the paths off of each bridge, you can see how the freeway bridges coming across the river will have an exit for M Street similar to the current exit, but it deposits drivers at M just west of 12th instead of using 12th itself. It also no longer has the neat little N Street cut-through directly from the ramp that some Navy Yard workers cherish. To get to the Navy Yard, drivers will turn left on M, then left at 11th, and then go to whichever gate they need.
Other information in the slides includes: a graphic showing of the new ramps and accesses on the east side of the bridges at 295 and MLK (slide 12), of which the biggest addition is that you'll now be able to get to and from 295 and the bridges in all directions. There's also recent construction photos (including the first structural steel being laid on the freeway bridge), and information on stormwater management areas, and upcoming traffic impacts (slide 19).
It's expected that the freeway bridge will open about a year from now, with the new local bridge being finished in the winter of 2012/2013. (Dr. Gridlock wrote about recent milestones and upcoming work a few weeks ago.)
If you want to know more, there's my 11th Street Bridges project page, and you can also spend a couple months reading the Environmental Impact Statement to see all the studying they did of potential, um, impacts. There's also this Fact Sheet that they handed out.
 

See All Current News Items

Comments

Rick says: (11/10/10 7:06 AM)
JD - link to fact sheet is broken.

JD says: (11/10/10 8:24 AM)
Thanks, fixed.


BillP says: (11/10/10 9:16 AM)
SO excited that the prior stupidity of (1) not being able to get on the SE/SW freeway from 295 South and (2) having to use Penn Ave to go from the SE/SW freeway to 295 North is being corrected.

I know JD has mentioned "odd" placement of freeway signs on 395 and the SE/SW freeway as they pertain to near SE. Has anybody heard if they are going to try to "name" or "number" the stretch of the SE/SW freeway after 395 north departs via tunnel and 295, especially now that these freeways will actually be properly connected in all directions?

Froggie says: (11/11/10 8:43 PM)
Bill: officially, the SE Freeway is I-695. Whether DDOT signs it or not after project completion is anybody's guess. Given current precedent, I expect them to sign it as "TO I-295/DC 295" or "TO I-395".

JD says: (11/11/10 8:46 PM)
695 is so Baltimore. :-)

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2014!

Tell readers about your
apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
Shogungts on Grosvenor Looking for: @JES- if you are going to get all technical about it, they s...
Sophia Monster on Lineups Announced for: "Rudy" was slated to give a motivational speech at...
smokie on Grosvenor Looking for: aw! Well fair enough.
JD on Grosvenor Looking for: My methods are proprietary. :-) (JES, fixed your link)
Latest News
  
For past mile markers in the neighborhood's evolution,
see my Near Southeast DC Timeline.

 
Thousands and thousands of photos showing the neighborhood changing. More than 150 buildings no longer with us. All the news, since 2003. Photos from various archives showing the neighborhood in the more distant past. Maps from the early 1900s. Overhead Photo Comparisons: 1949, 1988, 2002-2008. All Blog Entries, 2003 - Present Major Events, 1799 - Present A series of blog entries looking at the neighborhood's history.
Near Southeast's Rearview Mirror
Today in (Recent) Near Southeast History


City Government Data for Near Southeast
Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
100 B/O L ST SE   THEFT F/AUTO /  04/05/14
1500 B/O SOUTH CAPITOL ST   THEFT /  04/04/14
330 B/O K ST SE   THEFT /  04/04/14
16 B/O M ST SE   THEFT /  04/04/14
700 B/O L ST SE   THEFT /  04/03/14

Active Public Space Permits Archive  
1011 1ST ST SE    COLIN CLARK 
Pending
excavation; new  
 03/03/14
to
05/01/14
    COLIN CLARK 
Approved (Pending Payment)
paving; landscaping; new  
 04/23/14
to
06/27/14
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
1201 M ST SE    Michael Manoski 
Pending Document
excavation  
 05/06/13
to
05/05/14
1333 M ST SE    WASHINGTON GAS 
Assigned
excavation  
 05/01/13
to
04/30/14
1111 NEW JERSEY AVE SE    NJA Associates LLC 
Assigned
paving; streetfixture; landscaping; excavation; new  
 06/03/13
to
06/02/14
301 TINGEY ST SE    Chuchart Kampirapang 
Assigned
 
 06/07/13
to
06/06/14
    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
04/09/14 
MILLER?LONG
AH1400386 / CONSTRUCTION
AFTERHOURS TO TAKE DOWN TOWER CRANE WITH 200 TON CRANE SAT ? SUN 4 / 12 / 2014 AND 4 / 13 / 2014 FROM 5AM TO 9PM
   
04/21/14 
TOLL DC LP / DELAWARE ELEVATOR INC
EN1401543 / SHOP DRAWING
TYPE OF ELEVATOR : ONE (1) MRL / STEEL / FRONT OF BLGD / PASSENGER. (VELOCITY RIVER PARK / PLASE 2 / CAR A)
1381 1ST ST SE   
04/07/14 
DISTRICT OF COLUMBIA /
SB1400233 / CONSTRUCTION
INSTALLATION OF 3 GEO SOIL BORINGS TO A DEPTH OF 30FT 4' DIAMETER USING GEOPROBE 3 OUT OF 3 ARE TMMW
1212 4TH ST SE   
04/09/14 
GSA GSA / BRIAN FREW; GSA GSA; JOSEPH RICHARDS
E37554102 / SUPPLEMENTAL
1000 5TH ST SE   
04/04/14 
DC HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
B1404942 / CONSTRUCTION
TEMPORARY CONSTRUCTION TRAILER TEMPORARY CONSTRUCTION FENCE AROUND THE PERIMETER OF THE PROPERTY AND TWO PORTA POTTIES AND TO INCREASE TO A TOTAL OF 4 PORTA POTTIES AT THE PEAK OF CONSTRUCTION. TRAILERS WILL BE ON BLOCKED ON TEMPORARY CMU BLOCKS - POWERED FROM TEMPORARY SERVICE BY PEPCO TRAILERS WILL BE EQUIPPED WITH RESTROOM SYSTEM THAT WILL BE SERVICED - NO PLUMBING LINES AS THEY ARE SELF CONTAINED
   
04/11/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
SH1400015 / CONSTRUCTION
SHEETING ? SHORING FOR NEW COMMUNITY CENTER
1220 12TH ST SE   
04/15/14 
WASHINGTON GAS LIGHT CO / STEPHEN R. HOLMAN
P1404623 / SUPPLEMENTAL
1015 HALF ST SE   
04/09/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
B1405731 / CONSTRUCTION
INTERIOR RENOVATION FOR 1ST FLOOR SERVICE CORRIDOR. PARTITIONS DOORS MECHANICAL ELECTRICAL AND LIFE SAFETY.
75 I ST SE   
04/07/14 
DRI DEVELOPMENT SERVICES LLC / JOSE S ALVARADO; DRI DEVELOPMENT LLC; JOSE S ALVARADO
E16994763 / SUPPLEMENTAL
   
04/07/14 
DRI DEVELOPMENT SERVICES LLC / JOSE S ALVARADO; DRI DEVELOPMENT LLC; JOSE S ALVARADO
E10943636 / SUPPLEMENTAL
409 I ST SE   
04/07/14 
SCOTT A FAULK TRUSTEE / RALPH THREATT
E1404619 / SUPPLEMENTAL
309 K ST SE   
04/06/14 
GERRITT LANG
PC61450444 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 GAS APPLIANCE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
306 L ST SE   
04/17/14 
MICHAEL THOMPSON
B1311538 / CONSTRUCTION
1.CRAWL SPACE FOUNDATION REPAIR CRAWL SPACE UNDERPINNING AND EXCAVATION 2. ADD CONCRETE SLAB AND EGRESS WINDOW. 3. UPGRADE EXISTING ELECTRICAL PLUMBING AND MOVE MECHANICAL CLOSET
601 L ST SE   
04/21/14 
DC HOUSING AUTHORITY / ANGEL REYNOLDS
SH1400035 / CONSTRUCTION
TEMPORARY SHEETING AND SHORING REQUIRED TO ALLOW CONSTRUCTION PF NEW BUILDING AT 601 L ST SE.
50 M ST SE   
04/17/14 
KEN FINKELSTEIN ENGLEWOOD LLC / DAVID BOOKBINDE ECS MID-ATLANTIC LLC
SB1400244 / CONSTRUCTION
A TOTAL OF 6 BORINGS WILL BE ADVANCED ACROSS THE PROPERTY WITH A GEOPROBE DRILL RIG TO A DEPTH OF 25 FEET BELOW SURFACE GRADE. THE DIAMETER OF THE BOREHOLE WILL BE 2.25 INCHES. SOIL WILL BE SCREENED THROUGHOUT THE DEPTH OF EACH BORING AND EACH 5-FOOT COMPOSITE SAMPLE WILL BE ANALYZED. GROUNDWATER WILL BE COLLECTED FROM TEMPORARY WELLS IN THREE BORINGS IF ENCOUNTERED. ALL BORINGS WILL BE GROUTED WITH APPROVED BENTONITE SLURRY UPON COMPLETION. SEE WORKPLAN FOR ADDITIONAL DETAILS.
901 M ST SE   
04/14/14 
CARLTON RAY / DANIEL SCHAALE
AH1400397 / CONSTRUCTION
EXCAVATION IN ROADWAY
1201 M ST SE   
04/14/14 
CARLTON RAY / DANIEL SCHAALE
AH1400396 / CONSTRUCTION
EXCAVATION IN ROADWAY
   
04/14/14 
SAMUEL PAXTON
PC81065987 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 PLUMBING FIXTURE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
86 N ST SE   
04/17/14 
BELFAST VALLEY CONTRACTORS / KIM MITCHELL CDKM CONSULTING LLC
TC1400011 / CONSTRUCTION
ERECT TEMPORARY TOWER CRANE AT 1ST AND N ST SE
1000 NEW JERSEY AVE SE   
04/14/14 
PHILIP BROWN
PC47087282 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 GAS APPLIANCE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
1500 SOUTH CAPITOL ST SE   
04/07/14 
WASHINGTON NATIONALS STADIUM LLC / FRED GRIFFITH; WASHINGTON NATIONALS STADIUM LLC; JAY LIVESAY
E53144683 / SUPPLEMENTAL
301 TINGEY ST SE   
04/11/14 
NA NA NA
EHOP1490466 / HOME OCCUPATION
   
04/11/14 
NA NA NA
EHOP1490467 / HOME OCCUPATION
301 WATER ST SE   
04/04/14 
FC LUMBER SHED LLC / RICHARD V CAREY
P1404549 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Projects Underway
Twelve12/Yards
Park Chelsea
Southeast Blvd.
River Parc
  
Nationals Park
Visiting Nats Park
What's New Around the 'Hood
Food Options Map
Parking/Transportation
Ballpark Construction Photos
Stadium Event Photos
In the Pipeline
Hampton Inn
1111 New Jersey
800 NJ/Whole Foods
Lofts at Capitol Quarter
Ballpark Square
New Douglass Bridge
Yards at DC Water
Virginia Ave. Tunnel
99 M St.
Monument/Half Street
Community Center
Capper Apartments
250 M Street
Florida Rock
909 Half Street
Congressional Square
1000 South Capitol
SC1100
New Marine Barracks
Factory 202/Yards
Nat'l Comm. Church
Completed
Lumber Shed ('13)
Boilermaker Shops ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts/Yards ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 NJ Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
Nationals Park ('08)
70/100 I ('08)
Seniors Bldg Dem. ('07)
400 M ('07)
SoCap Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Overviews
Capper/Carrollsburg
Ballpark District
New Jersey Ave.
M Street
South Capitol St.
WASA
The Yards
Lower 8th Street
East M Street
Boathouse Row


Links of Interest

JDLand.com Wins 2008 Knight-Batten Citizen Media Award
As part of the Knight-Batten Awards for Innovations in Journalism, JDLand was given the 2008 Citizen Media Award. Read all about it.

Capitol Riverfront Business Improvement District
Covering Near Southeast & Buzzard Point.

Studies/Initiatives/Government Documents:
11th Street Bridges EIS
South Capitol St. Bridge EIS
South Capitol Gateway Corridor/Anacostia Access Study
Anacostia Riverwalk Trail
NCPC's New Vision for South Capitol Street (2005 Update)
Anacostia Waterfront Initiative (2005)
Near Southeast Draft Urban Design Framework (2003)
Urban Land Institute South Capitol Street Corridor Report (2003)
Neighborhood Strategic Action Plan (2002)
DC Streetcars (may run down M Street SE someday)

Capitol Gateway and Southeast Federal Center Zoning Overlays
Two documents that spell out in extreme detail exactly what the requirements are for developments along South Capitol, M, in the Ballpark District, and at "The Yards". Read also my short explanatory treatise on these two overlays.

Pre-Redevelopment Media Overviews:
A Transformed Neighborhood Awaits Stadium (WP, 8/15/05)
      includes huge map of development plans
The Morphing of a Forgotten Neighborhood (WP, 9/2/2004)
      A brilliant take on the neighborhood!
Betting Big on Near Southeast (WP, 7/15/04)
Hope for the Waterfront (WBJ, 01)
Seeking a Better View On the Waterfront (WP, 3/8/98)
 

DC Government
Mayor's Office
Planning/Economic Development
   Office of Planning
DC Consumer & Regulatory Agency
DC Office of Zoning
DC Municipal Regulations | Zoning
DC Dept. of Transportation

DC City Council
Tommy Wells

ANCs: 6D | 6B
David Garber (6D07)
Kirsten Oldenburg (6B04)
Police: MPD-1D | PSA 105

Other Organizations
National Capital Planning Commission
Earth Conservation Corps
Capitol Hill Restoration Society
Barracks Row Main Street
Marines Community Integrated Master Plan
 

 

News Publications
The Hill Rag
The Southwester

Other DC Neighborhood/City Blogs
SW DC - The Little Quadrant That Could
The Hill is Home
Congress Heights on the Rise
Greater Greater Washington
WashCycle
Penn Quarter Living
Frozen Tropics
The Triangle
14th and You
The 42
Beyond DC
Richard Layman
 




Top of Page | Contact JD | Advertise on JDLand
Near Southeast RSS Feed

© Copyright 2014 JD.
All photos © Copyright JD - See information on photo uses, licensing and purchasing.