The last Near Southeast item on Monday's ANC 6D meeting was a request for the commission's support of the latest design of
RiverFront on the Anacostia, better known as Florida Rock. This is the nearly six acres of land directly south of the
ballpark, on the Anacostia River, where developers have spent 10 years trying to transition away from the concrete business currently operating there to a 1.1-million-square-foot mixed-use waterfront destination. They came close to an approved design in 2006, but in February 2007 the
Zoning Commission unexpectedly sent the architects back to the drawing board, wanting a greater amount of residential space in the project, better views to and from the ballpark, and a better "expression of place."
After nearly a year, a revised design is ready to go to the Zoning Commission for approval. It now includes 323,000 square feet of residential space, 80,000 square feet of retail and 465,000 square feet of office space.
Some of the ideas floated
early in the redesign process have been modified or removed, most notably "The Pitch", the plaza directly across from the
ballpark's grand staircase and adjacent to the planned
Diamond Teague Park. This space no longer has pitcher and catcher statues but is instead now a "festive" open plaza that will be more "integrated" with Teague and will help with the expected flow of ballpark visitors coming to and from the water taxi piers that someday may materialize out by the little red brick pumphouse.
Also, the residential and hotel buildings have had their heights grow to 130 feet, to allow for the extra square footage the zoning commission wanted. But the hotel's top two floors will now be "pure residential".
As for when some movement will actually be seen at the site, David Briggs of Holland & Knight set out a timeline based on zoning approvals, construction drawings, and the vaunted DC permitting process that estimates the start of construction on the first phase (the eastern office building) in probably fall of 2009.
He mentioned a number of times the amount of pressure that Florida Rock is under to shut down the concrete plant and to build temporary parking lots, but he explained that the site currently makes money for its company and shareholders, and there's little interest in closing it down sooner than necessary. (Briggs did say that a temporary landscaping of the eastern plaza, next to Diamond Teague, could be a possibility once the zoning approvals are received, but that the underground parking for RiverFront does extend beneath that plaza, and so excavation and construction work will need to be done there.)
It should be noted that this timeline is really about the first two phases (the eastern office building and the 160-unit residential building), because the western office building and the hotel can't be built until the construction of
a new Douglass Bridge allows Florida Rock to use its land that is currently occupied by the old bridge. (The year 2016 was tossed around as a possible date for when these later phases could get started.)
Community benefits remain similar to past presentations, including an estimated 25 units of workforce housing, anticipated LEED certification for the buildings, First Source and LSDBE hiring, and a combined underground loading dock for the three western buildings, as well as the more basic amenity of replacing a huge concrete plant with shiny new buildings and access to the waterfront. The ANC has always been enthusiastic about this project, and this time around was no different, with the commissioners voting 5-2 to support the new design. The Zoning Commission hearing, for what is officially considered a modification to the project's second-stage PUD, is scheduled for March 20.
I'm really trying to just hit the newsiest items here--definitely take some time to look through my
RiverFront page (have to stop calling it Florida Rock sometime) for much more detail on the current design. And read all the
archived news items, too, if you want a better feel for the twists and turns this project has taken.