At Monday's ANC 6D meeting, representatives of MRP Realty made a presentation showing the updates to the RiverFront on the Anacostia project (aka Florida Rock) that they will be taking to the Zoning Commission later this year.
These designs are part of the quest to make changes to the original design approved by the commission in 2008, chief of which is to switch the first phase of the 1.1-million-square-foot mixed-use project from an office building to a 300ish-unit apartment building at 1st Street and Potomac Avenue, along with a series of other changes that I've written about previously. (Dear heavens, don't make me write it all again.)
Here are the slides that were presented by the developers, which should be of interest even without the accompanying narration. The renderings are much more detailed and "showier" than those given to the Zoning Commission back in February, which was part of what the developers were tasked with providing in their next go-round with the ZC.
Most obviously, the developers appear to have gotten the "more retail!" message that had been delivered pretty clearly at the last two zoning commission sessions on the new design, with 18,650 square feet of retail now covering most of the first floor of the Phase I residential building, bumped up from 12,520 sf in the previous version (some of which the developers had been wanting to mark off for "temporary resident uses" until the market for retail in the area could be proven). The entire site is now designed to have 48,360 sf of retail, but this is still down from the 64,200 sf that was in the plans approved by the Zoning Commission back in 2008. (This increase in retail also means that the "four red doors" facing Potomac Avenue that sent zoning commissioner Michael Turnbull through the roof back in February are now gone.)
There was also much time spent on the designs for the public spaces that span the 5.5-acre site. With large lawns, wetlands-type areas that would actually be bio-filtration mechanisms, quieter tree-covered spaces, and a marina that could potentially have 40-50 slips, the additions could be seen as echoing the Yards Park a couple blocks to the east.. But there are also some "beach" areas where sand would be placed, and a large sculpture could be included in the "Riverfront Plaza" at the foot of 1st Street. The esplanade is still a major part of the design, but there is no longer a separate bike path--pedestrians and cyclists would share the boardwalk as it runs through the entire site, from South Capitol Street to Diamond Teague Park. And there may even be locations where some of the concrete blocks from the old concrete plant site would be incorporated into the public spaces.
I could write more about the specifics, but since the project will be back in front of ANC 6D looking for a resolution of support in July, and then at the Zoning Commission on Sept. 20, I'd prefer to save some words for the presentations to come.
I've added some of the renderings from this presentation to my Florida Rock project page. And, when looking at all of this, remember that the western two buildings (phases 3 and 4, an office building and a hotel), are not be able to be built until the new South Capitol Street/Douglass Bridge is built a bit to the south of the current bridge, which now runs directly through the Florida Rock footprint. And there's as yet no timeline for that new bridge.
Comments (3)
 
 More About ANC News

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (5/16/12 11:30 AM)
This looks way much better than the first rendered design. I love the whole idea of beach and volley ball.
Is there any time table when they are going to start working on the new South Capitol Street/Douglass Bridge?


JD says: (5/16/12 11:42 AM)
As soon as they get the money. Altogether, with all of the additional work they want to do at the same time (new ramps/connections to both the SE/SW Freeway and to I-295), it's about a $800 million project. link



Sophia Monster says: (5/16/12 3:56 PM)
Sand from wall to wall. I know a great sand guy, we'll get it at price.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
JD on Ceremonial Groundbreaking for: It's still there, just not under the What's New for reasons I can't quite fathom...
MJM on Ceremonial Groundbreaking for: Previous post not there - interesting that only one building in that picture rem...
JD on Details and Drawings: {{scurrying to update map with rendering and correct new info}}
JD on History Events This: My sense was that the city is saying "we're moving forward with no swing span, b...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
200 B/O L ST SE   THEFT F/AUTO /  07/30/14
L ST SE AND 2ND ST SE   THEFT F/AUTO /  07/30/14
70 B/O I ST SE   MOTOR VEHICLE THEFT /  07/29/14
70 B/O I ST SE   THEFT /  07/29/14
1100 B/O NEW JERSEY AVE SE   THEFT /  07/28/14
400 B/O K ST SE   THEFT /  07/24/14
1000 B/O 1ST ST SE   THEFT /  07/23/14

Active Public Space Permits Archive  
1011 1ST ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 06/26/14
to
08/26/14
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
913 5TH ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
08/28/14
1100 - 1199 BLOCK 1ST ST SE    tom cash 
Issued
excavation; new  
 06/27/14
to
08/25/14
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
800 NEW JERSEY AVE SE    Pepco Holdings Inc 
Issued
excavation; new  
 06/20/14
to
08/22/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
08/06/14 
TOLL DC LP / MITCH A. PERMUY
E1407892 / SUPPLEMENTAL
   
08/11/14 
TOLL DC LP / ALBERT J. PEARCE
FB1400108 / SUPPLEMENTAL
1259 1ST ST SE   
08/11/14 
CAPITAL RIVERFRONT HOTEL LLC / CAPITAL RIVERFR HOTEL LLC
AH1400636 / CONSTRUCTION
AFTER HOURS FOR PERMIT NUMBER B1401471 FOR 8 / 12 THROUGH 9 / 11 FROM 5AM TO 7PM MONDAY THROUGH SATURDAY.
1212 4TH ST SE   
08/07/14 
TAKOREAN / FVI 2020
B1410615 / CONSTRUCTION
REVISION TO TL1400052 TO INCLUDE OUTDOOR SUMMER GARDEN WITH 14 SEATS AND 7 TABLES.
1201 4TH ST SE   
08/12/14 
JBG/FEDERAL CENTER LIC / JIM CALABRESE
AN1400129 / CONSTRUCTION
PLEASE EXTEND PERMIT AN1300174 THIS IS THE FIRST EXTENSION AND PERMIT WILL BE VALID UNTIL 1 / 31 / 2015.
1212 4TH ST SE   
08/01/14 
MIKE LENARD 1451 BELMONT ST NW SUITE 214 / PAUL THIEBERGER; MIKE LENARD 1451 BELMONT ST NW SUITE 214; PAUL THIEBERGER
P93379840 / SUPPLEMENTAL
   
08/05/14 
FC 1212 LLC / THE YARDS
TL1400165 / CONSTRUCTION
FIRST TIME TENANT LAYOUT FOR NEW MANAGEMENT OFFICE 2ND FLOOR TOTAL OF 780 SQ FT RENOVATION LIMIT TO MECHANICAL ELECTRIC AND FIRE LIFE SAFETY ONLY
1331 4TH ST SE   
08/14/14 
F. C. 1331 LLC / FVI 2020
B1402843 / CONSTRUCTION
CONSTRUCTION OF A BRAND NEW 11 STORY BUILDING. THE BUILDING IN TOTAL IS 350 000 SQ FT. ADDING 327 RESIDENTIAL RENTAL UNITS 20 000 SQ FT. IN COMMERCIAL SPACE AND 3 BELOW GRADE PARKING LEVELS.
   
08/15/14 
CLARK CONCRETE
AH1400650 / CONSTRUCTION
AFTER HOURS TO POUR CONCRETE ON JOBSITE FROM 7AM TO 7PM FROM SUNDAY TO SATURDAY 8 / 15 / 2014 TO 11 / 15 / 2014
1000 5TH ST SE   
08/07/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
FD1400029 / CONSTRUCTION
FOUNDATION TO GRADE TO INCLUDE UTILITIES
   
08/13/14 
UNITED STATES OF AMERICA /
FD1400132 / CONSTRUCTION
NEW FOUNDATION TO GRADE PERMIT FOR NEW COMMUNITY CENTER INCLUDING UTILITIES. REVISION TO FD1400029 TO REVISE STRUCTURAL DETAILS OF COLUMS.
1015 HALF ST SE   
08/12/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
TL1400162 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 1ST FLOOR PERFORMANCE STUDIO SPACE AND OFFICE SPACE. PARTITIONS FURNITURE MECHANICAL ELECTRICAL AND LIFE SAFETY. CBS
   
08/15/14 
HALF ST SE LLC / ROBERT L HUNTER
M1402951 / SUPPLEMENTAL
   
08/16/14 
SAM HOLLEN / DONALD VEALS; SAM HOLLEN; DONALD VEALS
E83010192 / SUPPLEMENTAL
1201 HALF ST SE   
08/01/14 
LIVE NATION / JOSE VEGA A-1 ENGINEERING
TN1400164 / CONSTRUCTION
TO PLACE A TENT IN PUBLIC SPACE FOR SPECIAL EVENT AT NATIONALS PARK
200 I ST SE   
08/08/14 
DANIEL RILEY / OMAR BIAGAS; DANIEL RILEY; JOHN BIAGAS
E47247428 / SUPPLEMENTAL
37 L ST SE   
07/31/14 
GRETA SILVERMAN / JAMES SILVERMAN
B1410329 / CONSTRUCTION
UPGRADE EXISTING ROOF
601 L ST SE   
08/06/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / JOSEPH M MAGNOLIA
P1407161 / SUPPLEMENTAL
20 M ST SE   
08/06/14 
SOUTHEAST REALTY LLC /
P1407613 / SUPPLEMENTAL
100 M ST SE   
08/06/14 
SQUARE 743 INC /
P1407610 / SUPPLEMENTAL
   
07/31/14 
SQUARE 743 INC. 100 M ST SE / PAUL THIEBERGER; SQUARE 743 INC 100 M ST SE; PAUL THIEBERGER
P83348948 / SUPPLEMENTAL
   
08/16/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
901 M ST SE   
08/14/14 
CARLTON RAY
AH1400642 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
08/14/14 
CARLTON RAY
AH1400641 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1100 NEW JERSEY AVE SE   
07/31/14 
SQUARE 742 LLC / SPRINT ADVANTAGE ENGINEERS
AN1400072 / CONSTRUCTION
AS PART OF SPRINT'S 2.5 MHZ LTE PROJECT SPRINT WILL BE ADDING ONE EQUIPMENT CABINET THREE PANEL ANTENNAS AND THREE REMOTE RADIO HEADS TO THE EXISTING WIRELESS TELECOMMUNICATIONS FACILITY
1111 NEW JERSEY AVE SE   
08/12/14 
NJA ASSOCIATES LLC / COLIN CLARK
B1308085 / CONSTRUCTION
CONSTRUCT A NEW 13 STORY APARTMENT BUILDING WITH THREE BELOW GRADE PARKING LEVELS FIRST FLOOR RETAIL A PRIVATE SWIMMING POOL PROJECTIONS OF BAY WINDOWS 324 UNITS TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND ELEVATOR WORK.
1500 SOUTH CAPITOL ST SE   
08/04/14 
LIVE NATION / DAVID VEGA
AH1400629 / CONSTRUCTION
TO CLOSE OFF STREETS FOR LOADING AND UNLOADING OF STADIUM EVENTS 7PM - 7AM
300 TINGEY ST SE   
08/05/14 
FC BOILERMAKER LLC / PHILLIP B MOBLEY
M1402818 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.