It's more than 100 pages of high finance and headache-inducing legalese, but nonetheless I've gotten my hands on the "Preliminary Official Statement" for what is expected to be a $29 million PILOT bond sale to fund a series of infrastructure improvements for future phases of the Capper/Carrollsburg redevelopment. (This is the document written for investors to help them decide whether or not to purchase the bonds.) If you want to know all about how these bonds are being structured (with monies from the Downtown TIF playing a part), this is the document for you. It also has some good background on the Capper project if you're just catching up.
But it also has a few tidbits on the current and projected path of some upcoming parts of the overall project, starting on page 19. Here are the items that are probably of most interest, with the usual caveats that no timeline is written in stone anymore:
* Financing for the second phase of Capitol Quarter is being negotiated and is expected to close in mid-2010. Development work would then begin in August, and vertical construction in November. (Phase 2 covers the blocks between Third and Fourth and I and M, and will contain 116 new for-sale townhouses and 47 public housing rental units.)
* All but five of the 121 CQ phase 1 townhouses have sold, and two of those are being held back as model units.
* Financing is "being negotiated" for the planned apartment building on the northern half of Square 882, the site that's been the subject of my recent posts on the Marines coveting the site as well. That financing is expected to close in late 2010 according to this document, with an expected completion date of the apartment building in April 2012.
This $29M bond sale is not the last one for Capper infrastructure; the city council approved a total of $55 million in bond funding back in 2006, and the document says that the city "expects" another bond issuance for the rest of the money, "though the timing of such issuance is currently uncertain" (page 10).
As for what exactly the monies will be funding, the document lays out the following (page 22), though this is for the entire $55 million, so it can't be said that this current $29 million offering will cover all this (which will bum out the people who see the phase "community center"). Some of this work would also happen on the streets surrounding Canal Park:
* Repairing and replacing underground water and utility lines;
* Repairing streets and streetscapes and adding landscaping;
* Demolishing the DPW building (and smoke stack!) at 900 New Jersey, relocating DPW's operations, environmental site remediations (remember, that site was operating as a trash transfer site as far back as 1905);
* Building I Street through to New Jersey Avenue; and
* Constructing the new community center at Fifth and K.
It's expected that the bonds will be "priced" this week, with the sale closing by the end of the month.
I hear rumors that DPW could be out of their site by next spring, as the search continues for a new home for their operations (and maybe is getting close to a resolution).
Comments (0)
 
 More About Capper

JDLand.com Home

Comments

incognito says: (3/22/10 3:45 PM)
It is subtle and wonky, but the canalparkdc.org website now has on their homepage the three dimensional model of the park as released by Studios architecture in their drawings. Uncertain how long ago this change was made but I do think it looks great. Now we just have to continue pushing for construction to begin asap and no later than the advertised September 2010.


bt says: (3/22/10 3:54 PM)
47 public housing rental units???? WHY? Aren't there enough? Are we encouraging people to be losers? I want to do nothing and live in a brand new housing community!! where do i sign up? what are the qualifications?


JD says: (3/22/10 3:58 PM)
The public housing component is the only reason why Capitol Quarter is being built in the first place. The entire redevelopment got a Hope VI grant from HUD to replace 700 units of public housing in a new development with the same 700 units plus another 800 market-rate units. 300 of the units were already built in Capper Seniors #1 and 400 M. The rest will be in the Capitol Quarter townhouses and in the 5 mixed-income apartment buildings.



Michael says: (3/22/10 4:25 PM)
Canal Park... little surprise that the Web site's link to the building schedule it broken )


Kenny says: (3/23/10 11:18 AM)
Isn't I Street already built to New Jersey Avenue? Or is my memory already failing me...


JD says: (3/23/10 11:19 AM)
Not from the east. I stops at Second/Canal, then starts again at New Jersey.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
yard resident since 09 on Something Appears to: The yellow tape was for window washers
202_cyclist on Reminder: @JES: And King Ribs could open another location on the grass square. Life woul...
202_cyclist on Reminder: @JES: And King Ribs could open another location on the grass square. Life woul...
JES on Reminder: I peered in there last night, they made it look nice with the wood flooring and ...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
200 B/O VIRGINIA AVE SE   MOTOR VEHICLE THEFT /  07/10/14
900 B/O HALF ST SE   THEFT F/AUTO /  07/10/14
100 B/O M ST SE   THEFT /  07/09/14
4TH ST SE AND L ST SE   ROBBERY /  07/08/14
800 B/O POTOMAC AVE SE   THEFT /  07/07/14
300 B/O K ST SE   THEFT F/AUTO /  07/07/14
1100 B/O NEW JERSEY AVE SE   THEFT /  07/05/14
100 B/O L ST SE   THEFT F/AUTO /  07/04/14
1100 B/O 2ND PLACE SE   THEFT F/AUTO /  07/03/14
2ND PLACE SE AND I ST SE   THEFT F/AUTO /  07/02/14
70 B/O I ST SE   ROBBERY / GUN  07/02/14
200 B/O I ST SE   THEFT F/AUTO /  07/02/14
400 B/O M ST SE   MOTOR VEHICLE THEFT /  06/30/14
UNIT B/O M ST SE   THEFT F/AUTO /  06/30/14
70 B/O I ST SE   THEFT /  06/29/14

Active Public Space Permits Archive  
1011 1ST ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 06/26/14
to
08/26/14
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
804 3RD ST SE    Maximiliano Villagra 
Issued
streetfixture; new  
 08/05/14
to
08/06/14
904 3RD ST SE    Janel Fitzhugh 
Issued
streetfixture; new  
 07/01/14
to
08/14/14
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
913 5TH ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
08/28/14
1100 - 1199 BLOCK 1ST ST SE    tom cash 
Issued
excavation; new  
 06/27/14
to
08/25/14
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
800 NEW JERSEY AVE SE    Pepco Holdings Inc 
Issued
excavation; new  
 06/20/14
to
08/22/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 06/17/14
to
08/17/14
    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
1105 NEW JERSEY AVE SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/13/14
to
08/11/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1025 1ST ST SE   
07/26/14 
NA NA NA
EHOP1490737 / HOME OCCUPATION
1100 1ST ST SE   
07/15/14 
NA NA NA
EHOP1490710 / HOME OCCUPATION
1212 4TH ST SE   
07/11/14 
FC 1212 LLC /
P1406926 / SUPPLEMENTAL
   
07/14/14 
MIKE LENARD / BHAR; W. SAKIE BHAR
SG1400363 / CONSTRUCTION
INSTALL ONE SET OF BUILDING SIGN ON TO EXISTING BUILDING
1331 4TH ST SE   
07/09/14 
UNITED STATES OF AMERICA / RONALD C. CAYTON
E1406628 / SUPPLEMENTAL
1103 9TH ST SE   
07/25/14 
ICP PARTNERS POTOMAC 810 LLC / TALBERT DOWLING
E1407537 / SUPPLEMENTAL
1220 12TH ST SE   
07/16/14 
FAIRBANKS MORSE ENGINE / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1409041 / CONSTRUCTION
INTERIOR ALTERATION TO EXISTING 2578 SF OFFICE SPACE. AFFECTED AREA LESS THAN 1000 SF TO CREATE DEMISING WALL AND MINOR ALTERATIONS TO PARTITION PLAN IN CONFERENCE AREA. MECHANICAL AND ELECTRICAL WORK INCLUDED.
326 L ST SE   
07/17/14 
NA NA NA
EHOP1490715 / HOME OCCUPATION
55 M ST SE   
07/16/14 
HINES GLOBAL REIT 55 M STREET LLC / TYRAN D. BRANNUM
E1407255 / SUPPLEMENTAL
20 M ST SE   
07/17/14 
SOUTHEAST REALTY LLC / JOHN GIUSEPPE-RAMCO
TL1400132 / CONSTRUCTION
FIRST TIME TENANT BUILDOUT FOR FAST FOOD ESTABLISHMENT - SUBWAY SANDWICH SHOP SEATING 41 AS SHOWN ON THE ATTACHED ARCH. MECH. PLUMB. ELECT AND FIRE PROTECTION DWGS. INTERIOR WORK ONLY.
55 M ST SE   
07/15/14 
HINES
B1409693 / CONSTRUCTION
INSTALL 6 AUTOMATIC DOOR OPERATORS LOCATED AT THE ELEVATOR LOBBIES BETWEEN THE 4TH-7TH FLOORS
901 M ST SE   
07/15/14 
CARLTON RAY
AH1400584 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
07/15/14 
CARLTON RAY
AH1400585 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
800 NEW JERSEY AVE SE   
07/14/14 
NEW JERSEY AT H LLC / COLIN CLARK
B1409654 / CONSTRUCTION
REVISION TO PERMIT #SH1400039 FOR A OWNERSHIP CHANGE
   
07/28/14 
WC SMITH CO. / COLIN CLARK
FD1400040 / CONSTRUCTION
FOOTINGS AND FOUNDATIONS TO GRADE FOR A FUTURE APARTMENT BUILDING
1000 NEW JERSEY AVE SE   
07/11/14 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / RICHARD G. FINFROCK
P1406902 / SUPPLEMENTAL
   
07/11/14 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / BRANDON K VIERNES
M1402531 / SUPPLEMENTAL
   
07/22/14 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / DONALD R. MCGLYNN
E1407426 / SUPPLEMENTAL
1236 SOUTH CAPITOL ST SE   
07/11/14 
1244 SOUTH CAPITOL RESIDENTIAL LLC / GEOCAPITOL ENGINEERING LLC
SB1400340 / CONSTRUCTION
WE PROPOSE DRILLING THREE SIX-INCH DIAMETER GEOTECHNICAL TEST BORINGS USING THE HOLLOW STEM AUGER METHOD TO EVALUATE THE SUBSURFACE CONDITIONS. THE PROPOSED TEST BORING DEPTHS WILL BE 80 FEET BELOW THE EXISTING GROUND SURFACE. DRILLING EQUIPMENT WILL BE DECONTAMINATED BETWEEN EACH HOLE TO AVOID CROSS CONTAMINATION THROUGHOUT THE SITE. UPON COMPLETION THE GEOTECHNICAL TEST BORINGS WILL BE BACKFILLE...
1244 SOUTH CAPITOL ST SE   
07/11/14 
1244 SOUTH CAPITOL RESIDENTIAL LLC / GEOCAPITOL ENGINEERING LLC
SB1400341 / CONSTRUCTION
WE PROPOSE DRILLING TWO SIX-INCH DIAMETER GEOTECHNICAL TEST BORINGS USING THE HOLLOW STEM AUGER METHOD TO EVALUATE THE SUBSURFACE CONDITIONS. THE PROPOSED TEST BORING DEPTHS WILL BE 80 FEET BELOW THE EXISTING GROUND SURFACE. DRILLING EQUIPMENT WILL BE DECONTAMINATED BETWEEN EACH HOLE TO AVOID CROSS CONTAMINATION THROUGHOUT THE SITE. UPON COMPLETION THE GEOTECHNICAL TEST BORINGS WILL BE BACKFILLED ...
300 TINGEY ST SE   
07/23/14 
CM-YARDS LLC / DWIGHT SMITH
B1408815 / CONSTRUCTION
INSTALL OUTSIDE SEATING SUMMER GARDEN.
201 TINGEY ST SE   
07/11/14 
JBG COMPANIES / GEORGE DELGADO
B1409541 / CONSTRUCTION
ONE DAY SPECIAL EVENT FOR BMW SHOW--150 OCCUPANTS EXTERNAL GENERATOR RESTROOMS AND LIGHTING BAY DOORS TO REMAIN OPEN DURING FUNCTION
   
07/22/14 
JBG/SEFC 170 LLC / MICHAEL B. BELL
E1407422 / SUPPLEMENTAL
300 TINGEY ST SE   
07/10/14 
FORREST CITY AT THE YARDS / CRIS FLACK
TL1400123 / CONSTRUCTION
REVISION TO B1402734 FOR REVISIONS TO MECHANICAL AND ELECTRICAL SYSTEMS.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.